Client: Community Windpower Ltd
Contract Period: 11 Months
Value: £7 Million
Location: East Lothian (3 km South of Innerwick and 9.5 km South of Dunbar).

Project Details:

This project is being undertaken by Gael Force Renewables Ltd, which is a Joint Venture between William & Henry Alexander (Civil Engineering) Ltd, McLaughlin & Harvey Ltd and Barr Holdings Ltd.

  • 19 No. Siemens 3.0MW Turbine Foundations
  • 11 Miles of Site Roads
  • 19 No. Crane Hardstands
  • 5 No. Culvert Crossings
  • Substation
  • Cable trenching
  • Scottish Power Platform